Østensjø, Bygg nr. 415 & 416 ved Astilleros Balenciaga, Service Operation Vessels "Edda Brint" & "Goelo Enabler"

Edda Brint ifølge Edda Wind sin 2.kvartalsrapport nå planlagt overlevering i begynnelsen av 2023 pga. forsinkelser på gangway.
 
 
"Edda Brint" inn til Montrose Tordag i forrige veke
EddaBrint01.jpg


EddaBrint02.jpg

Begge foto: Dave Dodds
 
416 er forsinket på grunn av økonomiske problemer ved verftet. Blir ikke levert før q124.

Fra kvartalsrapporten.

C416 being built at Balenciaga, Spain, is unfortunately further delayed due to the earlier reported financial difficulties at the yard. To secure the delivery, Edda Wind will take a more active role in the completion of the vessel, including participation in the financing of remaining work, taking legal title as well as planning and project management related to the progress of work onboard. We aim to take delivery of the vessel in Q1-24.
 
Last edited:
 

Goelo Enabler – delayed commencement of operation​

Haugesund, 7 May 2024: Edda Wind ASA (“Edda Wind” or the “Company”) last night received a report of an incident during the Harbor Acceptance Test of the gangway system for Goelo Enabler (the “Vessel”). There have been no personnel injuries, but the incident will result in delayed operational start for the Vessel, which was set to start in May. An investigation has already been initiated by Edda Wind, and although this investigation is in its very early stages and no conclusion has been reached, a preliminary assessment indicates that this is an isolated incident and unrelated to the challenges Edda Wind has previously experienced with its gangway systems. Edda Wind will provide more detailed information as and when this becomes available and relevant.
 